Ethiopia-Sudan Power System Interconnection Project (Assosa-New Raback, New Jabel Awelya)

PIDA Code: BIP_EAPP_001

Project Overview

Length of transmission lines: 590 km;

Voltage: 500 kV double-circuit;

Sub-stations : Grand Renaissance (Ethiopia)-New Rabak, New Jabel Aulia (Sudan);

Number of people given access to electricity: XX People;

Number of Direct Beneficiaries: XX People;

Project Cost: USD 440,000,000;

Project Program: Nile River Basin Investment Program (NRBIP).

Description

The Ethiopia-Sudan Power System Interconnection Project (Grand Renaissance-New Rabak, New Jabel Awelya) connects power generated by Ethiopia's Grand Ethiopian Renaissance Dam (GERD), via Assosa, to new substations at Rabak and Jebel Aulia near Khartoum in Sudan.
The Ethiopia-Sudan Power System Interconnection Project involves constructing a 590 km, 500 kV high-voltage transmission line linking Ethiopia's Grand Renaissance Dam (GERD) with Sudan's power grid, terminating at new substations in Rabak and Jebel Aulia near Khartoum. This interconnector is designed to facilitate the export of clean hydropower from Ethiopia's GERD, with a generation capacity of 5,150 MW, to Sudan, enabling Sudan to reduce reliance on thermal power and lower greenhouse gas emissions. The project includes upgrading substations at GERD, Rabak, and Jebel Aulia, and aims to improve power supply reliability and meet peak demand variability between the two countries. It is a key component of the Eastern Nile Power System and the continental PIDA program, promoting.

Stakeholders

Eastern Africa Power Pool (EAPP) 17

Project Information

Sector: Energy
Sub-Sector: Power Interconnector
Status: Active
Stage: N/A
Regions: East Africa

Want Full Access?

Register to view complete project details, financial information, and more.

Get Started