DURBAN – GAUTENG (NATCOR)

Project Overview

EXPANSION FROM 37 TO 105mtpa

Description

<p>This sub-programme aims to increase capacity on the corridor to match the forecasted demand. It involves train control (signalling) upgrading along the corridor, upgrading Rietvalleito Glencoe section to 26t axle load , construction of new rail link line connection from Cato ridge to Durban, converting the electrification from 3 kV DC to 25 kV AC, transformer replacement from Rietvalleito Booth, and improving the connectivity of the rail network with existing and proposed intermodal terminals along the corridor (including Harrismith)<br />
Development Strategy:<br />
Short term: 2013 -2025: 37 to 58mtpa<br />
-Additional block splits to allow for more trains<br />
-Increase loops to accommodate 75 Wagon Trains<br />
-Electrical supply (3 kV DC) and transformer upgrades<br />
Medium Term: 2025-2035: 58 to 95mtpa<br />
-Relieving of gradients and curves<br />
-Upgrade of Johannesburg to Newcastle section to 25kV AC<br />
-Increase loops to allow 150 wagon trains<br />
CHALLENGES<br />
-This Sub-Programmeis not currently funded.<br />
-Complementary investments required by road to service local traffic/freight.<br />
-Clarity on role of Harrismithfreight hub -provincial. government initiative to service Free State agriculture.<br />
-Clarity on role of Cato Ridge freight hub -provincial government initiative for a more back of port system.<br />
STATUS QUO<br />
-The concept (FEL -1) study is complete.<br />
-Extensive work underway to align demand and capacity with SIP 2 requirements.<br />
-Phase 1 has been defined and is awaiting technical validation from TFR.<br />
-Busy revising Plans according to latest Demand Forecast.<br />
-Programmeunfunded.<br />
-Programmedelayed due to shift in demand<br />
CONTACT: Gideon Coetzee<br />
PROJECT DESCRIPTION<br />
CORPORATE PLAN 2018/19<br />
18/19<br />
19/20<br />
20/21<br />
21/22<br />
22/23<br />
Total for 5 years (Rm)<br />
DPCT TP06 -Isipingoand Kaalfontein-Expand<br />
-<br />
-<br />
10<br />
-<br />
-<br />
10<br />
Total<br />
-<br />
-<br />
10<br />
-<br />
-<br />
10<br />
Feb 2018<br />
2a:DURBAN -GAUTENG (NATCOR)<br />
EXPANSION FROM 37 TO 105mtpa<br />
Long term:2035 -2041: 95 to 105mtpa<br />
-Migration to CBA (in cab) train control<br />
-Cato Ridge to Durban new bypass line and modifications to segregate PRASA from TFR services in order to free up capacity on the NATCOR</p>

Stakeholders

South Africa - Transnet (TRANSNET) 13

Project Information

Sector: Transport
Sub-Sector: Railway
Status: N/A
Stage: N/A

Interested in investing?

Contact the AUDA-NEPAD investment desk for project information, documents and an introduction to the sponsor.

Express investment interest

Want Full Access?

Register to view complete project details, financial information, and more.

Get Started